Updated planning of the DE-AT-PL-4M MC (Interim Coupling) Project
Vienna, Berlin, Warsaw, Prague, Budapest, Bucharest, Bratislava
10th May 2021
The Nominated Electricity Market Operators (NEMOs) and Transmission System Operators (TSOs) from Austria, Germany, Poland, and the 4M Market Coupling (4M MC) countries, namely the Czech Republic, Hungary, Romania, and Slovakia, hereby inform stakeholders about the slight update of the project planning.
Project parties have successfully completed the first phase of joint regional testing (Full Integration Testing - FIT) at the end of February 2021. The following phase of the testing (Simulation Integration Testing – SIT) focusing on the testing of regional operational procedures has started on 22nd March 2021. The regional SIT tests were originally planned to be finalized until 4th May 2021. Project parties have decided to prolong this regional testing phase by one week in order to enable additional testing to ensure robustness and reliability of the delivered solution. The updated planning was also coordinated with the relevant National Regulatory Authorities and with the SDAC parties.
As a result of this slight update in the planning, the regional tests are now expected to be completed until 12th May 2021, which will be followed by end-to-end procedural tests at a wider European level, together with all parties of the SDAC. The Member Tests with the participation of market participants are now envisaged to be carried out between 31st May 2021 and 7th June 2021.
Test plan
31.05.2021 |
Normal Day |
01.06.2021 |
Full decoupling incl. Shadow Auctions performed by JAO |
02.06.2021 |
Partial decoupling incl. Shadow Auctions performed by JAO (CZC related reasons) |
03.06.2021 |
Partial decoupling incl. Shadow Auctions performed by JAO (OBK related reasons) |
07.06.2021 |
Second Auction |
JAO will centrally organize the Shadow Auction on all ICP borders. In order to participate in the Member Tests, market participants need to register with JAO. More information on registration and Member Tests is available on www.jao.eu.
The go-live of the project is now planned for 17th June 2021 (first trading day, with the delivery day on 18th June 2021), subject to confirmation of technical and legal readiness by all parties.
The project parties remain fully committed to delivering the Interim Coupling, marking a milestone for the completion of the European Single Day-Ahead Coupling (SDAC).
*******
The DE-AT-PL-4M MC Project also referred to as Interim Coupling aims to connect the borders of 4M MC with the Multi-Regional Coupling (MRC) by introducing Net Transmission Capacity based (NTC-based) implicit capacity allocation on six borders (PL-DE, PL-CZ, PL-SK, CZ-DE, CZ-AT, HU-AT). This will mark the start of the so-called “enduring phase” of SDAC, during which there will be one European Single Day-Ahead Coupling only, where MRC and 4M MC are coupled.
Press release in PDF format available here.